Hafez Bridge in Karaj
The traffic and crossing of vehicles on Hafaz square in Karaj lack the necessary safeties, particularly the entrance into the Hafez Square from Char-Hesar (the continuation of Chaloos- Karaj path) is so risky. In order to solve this problem and secure Char-Hesar crossing and Shahid Modarres Boulevard (Khalaj Abad), construction of a non-coplanar bridge over this boulevard was put on the agenda. Hafez Bridge, Technical buildings and the intersection of paths at the end of Modarres Boulevard and the intersection of line 4 of Hesar with Shahid Modarres Boulevard put into operation.
General specifications and project volumes:
- Type of contract: Design, Supply of materials and construction (EPC)
- Client: Municipality of Karaj
- Consulting Client: Gozar-Rah Consulting Engineers
- Consulting Partner: Rahab Consulting Engineers
- Start date of operations: March 2012 (Farvardin1391)
- Duration of the contract: 12 months
- The length of main bridge: 75.5 m
- The largest bridge span: 33.40 meters
- The roadway width on the main bridge: 10.5 m
- The number of access ramps: 2
- The number of piers in main and side bridges: 3
- The total length of main and secondary routes: 250 m
- Type and stability system of the bridge: metal structure with composite slab
- The area of the bridge deck: 900 square meters
- The volume of concrete placement: 1600 cubic meters
- The weight of Reinforcement: 1100 tons
- The area of formatting: 7000 sq.m
Project information
Project location:
Alborz, Karaj
Alborz, Karaj
Area:
2
2
Execution project type:
Road
Road
Project start date:
WEDNESDAY, 21 MARCH 2012
WEDNESDAY, 21 MARCH 2012
Project Finish date:
THURSDAY, 21 MARCH 2013
THURSDAY, 21 MARCH 2013